JEL Maintenance Pte Ltd

JEL group of companies

Turbine Maintenance

501F Mitsubishi Gas Turbine Inspection & Overhaul Fond Der Power Plant, Taiwan
Turbine Maintenance

Major overhauling of both gas and steam turbine was carried out with manpower of 3 Technical Advisors and 50 technicians. This project was completed in 35 days with 2 shifts working round the clock. All the works were carried out under supervision of OEM representative.

GE GT Frame 6 - Hlawga Power Plant Overhaul, Myanmar
Turbine Maintenance

Major overhaul of entire GT including Refurbishment of Turbine rotor and rotor balancing was carried with the manpower of 5 TA and 25 technicians. All the technicians were hired locally for this project which was completed and handed over in 50 days.

29.6 MW Mitsubishi Steam Turbine Overhaul at Tuas Incineration Plant, Singapore
Turbine Maintenance

The team involved 2 TA, 3 Technicians, 20 fitters and 20 general workers to complete the ST overhaul in 30 days under supervision of Mitsubishi Japan.

701D Mitsubishi GT Inspection & Overhaul at AI-AWEER Power Plant, Dubai
Turbine Maintenance

Team involved 2 TA and 14 Technicians to carry out overhaul, rotor assembly modification and hot gas pass inspection (HGPI). This project was completed in very tight schedule working round the clock in 2 shifts and was completed in 15 days.

701F MHI GT Assembly for Tuas Power Plant at JEL Workshop, Singapore
Turbine Maintenance

Rotor assembly for 240 MW Gas Turbine at Tuas A Stage 2 Power Station, Singapore (1 Unit; Weight = 370 Tons) (Client/Owner: MHI Takasago/Black & Veatch/Tuas Power)

GE270 T732 ST Erection at Kerawalapitiya Power Plant, Sri Lanka
Turbine Maintenance

This project was completed in 5 months with manpower of 10 engineers & supervisors and 150 locally hired workers. The erection of turbine was headed by our engineers under the supervision of GE.

TA Supply for 701F HGPI Maintenance Works at Cestelnou, Spain
Turbine Maintenance

The work involved Rotor alignment, hot gas pass inspection and nozzle replacement under our TA supervision. This inspection service was completed in 14 days.

ABB Steam Turbine & Generator Overhaul At Sembcorp Cogen Plant for Alstom
Turbine Maintenance

A team of 60 including 8 supervisors under the supervision of Alstom were involved working round the clock in completion of this project in 30 days.