Jimma: HP Heater Replacement Works, Malaysia
Project Details:
Project Name: HP Heater #5 Replacement works
Owner: Jimma Unit 20
EPC Contractor: TPSC Engineering (M) Sdn Bhd
Project Duration: Mar 2016 – Aug 2016
Critical Works:
- New HP header weight 85 Tons
- Proper Cutting plan for pipes and rigging works were challenging
- All the Inter connecting pipes were under stress due to operation for more than 8 years
- Temporary arrangements were done to lock the pipe joints