Major Turn Around works in TPC SPEL

Major Turn Around works in TPC SPEL

Plant Owner: TPC
Main Contractor: JEL MAINTENANCE PTE LTD
Project Duration: July 2016 – August 2016
Man-hours: 150,000

Scope of Work:

  • Overhauling of Static & Rotating Equipment
  • Peak Manpower – 500 pax
  • Duration – 20 Days

Critical Works:

  • This shutdown was carried out on 4 plants BL1, BL2, TREX and SPEL-2.
  • Overhauling of more than 400 equipment, manholes, safety valves, reactor, drum, heat exchangers, filters, 4 extruders, 11 blowers, 2 compressors and various pumps and agitators, were carried out.
  • Manpower required for this shutdown works was 500. With the short time frame of only 20 days and working with such huge manpower, the job proved to be a challenge—one that JML has successfully overcome.