Sembcorp: Successful completion of Air Pre-heater replacement at EfW plant, Singapore

JML was awarded the replacement of Air Pre-heater (2 units) works at EfW Plant, Sembcorp Singapore. The total project period was for 6 months and the shutdown period was 21 days per unit. Both the units were successfully completed on schedule. We successfully clocked 75,000 manhours without LTI. Mr. Nagappan, CEO JML, joined the celebration

Sembcorp: Successful completion of Air Pre-heater replacement at EfW plant, Singapore Read More »

NSRP: Successful Completion of DCSM Package

DCSM Package-3 was awarded to us by Nghi Son Refinery and Petrochemical Limited Liability Company (NSRP) in September 2019, which has been successfully and safely completed last week. The scope of work included all mechanical works including the removal and re-installation of Pressure Safety Valve (PSV). The most challenging job of the package was the